Notice of road work: Telford and New Brailey Lines, Cox Drive, and Huffman and Soules Roads
About this project
Township of Severn is undertaking asphalt resurfacing and culvert replacements beginning May 6, 2024 in the areas of:
- Telford Line (from Centre Avenue to Stockdale Road)
- Telford Line/Soules Road overpass
- New Brailey Line (from Stockdale Road to Cambrian Line)
- Cox Drive and Huffman Road
The work is expected to be complete by Fall 2024.
This infrastructure project will improve the quality of the road for drivers. To learn more about how Severn is enhancing our road network visit our Plan, Reports, and Studies page to view our Roads Need Study (2022) and our Active Transportation Plan (2023).
Impacts to road users and residents
To complete the asphalt resurfacing and road crossing culvert replacement, daytime single-lane restrictions will be in place as required. These will be managed using signage and flag persons. At the end of each workday, the road will reopen as two lanes.
Short duration road closures may be needed for the installation of cross culverts. Notice of road closures will be posted in advance on our website and signage posted in the project area.
Access to private driveways and entrances will be maintained. At the end of each workday, the road will reopen as two lanes. At times, the work area will be gravel before paving which will result in temporary uneven road surfaces.
Staff contact
Colt Newman, C.E.T.
Manager of Capital Projects
Phone: 705-325-2315 x254
Email Colt